top of page
Search

How to Calculate the TMT Rods Required for a Building

  • Writer: arunbalajee
    arunbalajee
  • Dec 15, 2025
  • 2 min read

TMT (Thermo-Mechanically Treated) steel bars are the backbone of RCC construction. Calculating the correct quantity helps avoid steel shortages, excess wastage, and cost overruns.

This guide explains simple site-level methods as well as standard thumb rules used by engineers.




Things You’ll Need

  • Structural drawings (if available)

  • Built-up area (sq ft or sq m)

  • Type of structure (residential / commercial)

  • Diameter of TMT bars used

  • Unit weight chart for steel

Method 1: Thumb Rule Method (Fast Estimation)

This method is used for initial budgeting before detailed drawings.

Steel Requirement per Square Foot

Type of Building

Steel Quantity

Single-storey house

3.0 – 3.5 kg/sq ft

G+1 Residential

3.5 – 4.0 kg/sq ft

G+2 to G+4 Residential

4.0 – 4.5 kg/sq ft

Commercial building

4.5 – 6.0 kg/sq ft

Example

  • Built-up area: 2,000 sq ft

  • Steel factor: 4 kg/sq ft

Total steel required = 2,000 × 4 = 8,000 kg (8 tons)


Method 2: Detailed Calculation Using Structural Drawings (Accurate Method)


This is the recommended method for execution.

Step 1: Identify RCC Components

Steel is used in:

  • Footings

  • Columns

  • Beams

  • Slabs

  • Staircase

Each element has specified bar diameters and spacing.

Step 2: Calculate Steel for Each Component

Formula for Steel Weight

Weight (kg)=

D^2 / 162 X Length ( m )


Where:

  • D = Diameter of bar in mm

  • 162 = Constant for steel density


Step 3: Unit Weight of Common TMT Bars

Bar Diameter

Weight (kg/m)

8 mm

0.395

10 mm

0.617

12 mm

0.888

16 mm

1.58

20 mm

2.47

25 mm

3.86

Step 4: Example – Slab Steel Calculation

  • Slab size: 5 m × 4 m

  • Main bars: 12 mm @ 150 mm spacing

  • Distribution bars: 10 mm @ 200 mm spacing

Main bars

  • No. of bars = 4 ÷ 0.15 = 27 bars

  • Length per bar = 5 m

  • Weight = 27 × 5 × 0.888 = 119.88 kg

Distribution bars

  • No. of bars = 5 ÷ 0.20 = 25 bars

  • Length per bar = 4 m

  • Weight = 25 × 4 × 0.617 = 61.7 kg

Total slab steel = 181.58 kg

Method 3: Percentage Method (Quick Site Check)

Steel percentage in RCC:

  • Residential buildings: 1% – 1.5% of concrete volume

  • Commercial buildings: 1.5% – 2.5%

Example

  • Concrete volume: 100 m³

  • Steel %: 1.5%

Steel = 100 × 0.015 × 7850 = 11,775 kg

(7850 kg/m³ is steel density)

How Many TMT Rods to Order?

Standard Rod Length

  • 1 rod = 12 meters

Example

  • Total steel: 8,000 kg

  • Using 12 mm bars (0.888 kg/m)

Total length = 8,000 ÷ 0.888 = 9,009 mNumber of rods = 9,009 ÷ 12 ≈ 751 rods

Tips to Reduce Steel Wastage

  • Order diameter-wise quantities

  • Avoid random cutting on site

  • Reuse cut pieces for stirrups

  • Maintain bar bending schedules (BBS)

Common Mistakes to Avoid

  • Using thumb rules for final execution

  • Ignoring lap length and wastage (add 3–5%)

  • Mixing different bar grades randomly

  • Not matching steel grade with structural design

Final Advice

  • Use thumb rules only for cost estimation

  • Always rely on structural drawings and BBS for actual procurement

  • Consult a structural engineer for multi-storey buildings

 
 
 

Comments


bottom of page