How to Calculate the TMT Rods Required for a Building
- arunbalajee

- Dec 15, 2025
- 2 min read
TMT (Thermo-Mechanically Treated) steel bars are the backbone of RCC construction. Calculating the correct quantity helps avoid steel shortages, excess wastage, and cost overruns.
This guide explains simple site-level methods as well as standard thumb rules used by engineers.

Things You’ll Need
Structural drawings (if available)
Built-up area (sq ft or sq m)
Type of structure (residential / commercial)
Diameter of TMT bars used
Unit weight chart for steel
Method 1: Thumb Rule Method (Fast Estimation)
This method is used for initial budgeting before detailed drawings.
Steel Requirement per Square Foot
Type of Building | Steel Quantity |
Single-storey house | 3.0 – 3.5 kg/sq ft |
G+1 Residential | 3.5 – 4.0 kg/sq ft |
G+2 to G+4 Residential | 4.0 – 4.5 kg/sq ft |
Commercial building | 4.5 – 6.0 kg/sq ft |
Example
Built-up area: 2,000 sq ft
Steel factor: 4 kg/sq ft
Total steel required = 2,000 × 4 = 8,000 kg (8 tons)
Method 2: Detailed Calculation Using Structural Drawings (Accurate Method)
This is the recommended method for execution.
Step 1: Identify RCC Components
Steel is used in:
Footings
Columns
Beams
Slabs
Staircase
Each element has specified bar diameters and spacing.
Step 2: Calculate Steel for Each Component
Formula for Steel Weight
Weight (kg)=
D^2 / 162 X Length ( m )
Where:
D = Diameter of bar in mm
162 = Constant for steel density
Step 3: Unit Weight of Common TMT Bars
Bar Diameter | Weight (kg/m) |
8 mm | 0.395 |
10 mm | 0.617 |
12 mm | 0.888 |
16 mm | 1.58 |
20 mm | 2.47 |
25 mm | 3.86 |
Step 4: Example – Slab Steel Calculation
Slab size: 5 m × 4 m
Main bars: 12 mm @ 150 mm spacing
Distribution bars: 10 mm @ 200 mm spacing
Main bars
No. of bars = 4 ÷ 0.15 = 27 bars
Length per bar = 5 m
Weight = 27 × 5 × 0.888 = 119.88 kg
Distribution bars
No. of bars = 5 ÷ 0.20 = 25 bars
Length per bar = 4 m
Weight = 25 × 4 × 0.617 = 61.7 kg
Total slab steel = 181.58 kg
Method 3: Percentage Method (Quick Site Check)
Steel percentage in RCC:
Residential buildings: 1% – 1.5% of concrete volume
Commercial buildings: 1.5% – 2.5%
Example
Concrete volume: 100 m³
Steel %: 1.5%
Steel = 100 × 0.015 × 7850 = 11,775 kg
(7850 kg/m³ is steel density)
How Many TMT Rods to Order?
Standard Rod Length
1 rod = 12 meters
Example
Total steel: 8,000 kg
Using 12 mm bars (0.888 kg/m)
Total length = 8,000 ÷ 0.888 = 9,009 mNumber of rods = 9,009 ÷ 12 ≈ 751 rods
Tips to Reduce Steel Wastage
Order diameter-wise quantities
Avoid random cutting on site
Reuse cut pieces for stirrups
Maintain bar bending schedules (BBS)
Common Mistakes to Avoid
Using thumb rules for final execution
Ignoring lap length and wastage (add 3–5%)
Mixing different bar grades randomly
Not matching steel grade with structural design
Final Advice
Use thumb rules only for cost estimation
Always rely on structural drawings and BBS for actual procurement
Consult a structural engineer for multi-storey buildings



Comments